How to properly remove a requirement/user story/task from a running sprint?

How to properly remove a requirement/user story/task from a running sprint?

Half way through the sprint we realized that we won't be able to achieve the sprint goal, so the product owner decided, that one of the bigger features will be taken out of the running sprint.

This is how agilo renders the burndown chart, when we remove the sprint property value from the user story.

Before the user story has been taken out:


After the story has been taken out:


The problem I see with this is: The interpretation of the burndown chart now doesn't reflect the fact, that a user story was taken out from the sprint. In fact, now it looks like the task was never there in the first place. What we want to see there is a sharp vertical decline that would correctly reflect the removal of the user story.

Is there another option of removing user stories? Are we doing something wrong?

Thanks for the answer, and thanks for making Agilo. It's helping us immensely.
 