Allocate resources on task during a part of it.

within a task, allow a resource to work only in a time period.
Example : I have two tasks starting in the same time - one of 10 men days and one of 20 men days.
The resource #1 works on task #1 and res. #2 on task #2.
When task #1 is finished, I want to assign resource #1 on Task #2.
Thus Task #2 will be done in 15 days.