Gantt chart 5 days ahead of the task list

In my Gantter chart, each line in the Gantt chart is five days ahead of the dates listed in the task list:

1. Create task, start 4th November 2013, duration 5d.
2. Gantt chart shows task start on the Saturday of week beginning 4th November 2013, i.e. 9th November 2013.

Is this a bug, or a problem with my file?

I imported the original file from MS Project and have been saving to Google Drive.

I'm trying to sell the idea of using Gantter for all our projects to the directors, but this is quite broken.