how to assign the task of the weekend?

Hello,
Tell me please :
how to assign the task of the weekend?
2 people have
this question
+1
Reply
  • From Calendar Properties, select the weekend date that needs to be worked. In the Working Time box enter the times in the same format as shown on working days, e.g. 8:00 AM

    This means that every resource using that calendar will be scheduled that weekend.

    If you want all resources to work every weekend during the project, from Calendar Properties open Working Time Setup, select All Saturday by default and enter the working times for Saturday.

    If you want only some resources to work weekends, then create a new Calendar e.g. Weekend, define the working times as above. On the Task view, select the task(s), hit the Properties cog and from the Advanced tab, assign the Weekend calendar to that task.