Question: "Is possible to update the progression of the Project daily?"

Does gantter keep track of the current Date? I mean if i don't complete a Task the day after that i planned it, is possible to move it automatically to the day after? You can do this with the %complete! If a task is 100% it won't be moved to the days after, otherwise it will until it get done!

In this way the End date is Calculated after the "% complete" of each task!