Reschedule remaining work

I would like to be able to update all remaining work based on the current date as an option (not automatic). Either a setting that is project specific or apply on demand (preferred).
This way I can update % complete then "apply" the reschedule option and gantter will recalculate timelines based on incomplete and not started tasks. If a task was due to complete before today but is not set as 100% complete it's end date will move to today with all dependent tasks adjusting as appropriate. Also tasks with 0 (zero) % complete due to start before today now use today as a start date with duration remaining unchanched (giving a recalculated end date).
My new project timeline and estimated completion date would be calculated for me.
I believe on Openproj this is called "reschedule remaining work after"