Resource Calendars are always ignored

I am working on a project that involves 3 resources in different countries, working part time and all of them with different calendars.
I set the general calendar to 24/7 and took the job of creating a calendar for each resource.
The only calendar Gantter responds to is the project calendar.

Is there any way to run the project on different calendars for each resource?

Thanx,

Simon.

[UPDATE]: I go to task properties and assign the calendar I want, then press the save button. Nothing happens. When I go to task properties again, the calendar option says "NONE"