This is a marvelous product. Just 1 issue - Resource overbooking calculation.

I have 2 tasks starting at same time therefore being done in parallel:

Task 1: Duration 80h, Resource 1: 80%
Task 2: Stating at same time as Task 1. Duration 8h. Resource 1:100%

Gantter says resource is overbooked - How is the resource allocation calculated? Resource 1 is spending 64h on Task 1 and 8h on Task 2 - Total of 80h available and 72 allocated over 2 tasks and gantter says Resource is overbooked