Start project when external event has occurred (on an unknown date)

Hi,

I'm looking for a way to add some kind of constraint to a task. Typically, I've done some planning work, and I'm waiting for the client to come back and approve/review. The next task can't start until that's happened, and it would be great to somehow mark tasks that are waiting on third part feedback/approval, when this isn't necessarily linked to a specific date.

What's the best way to achieve this?

Thanks,

Lizzie